Showroom makeover daily journal #3

Captain's Log; star date Monday 1st August

Today saw Barry's (chippy) debut in the Flooring Guru's retail showroom makeover.  He played a blinder, too.  New door frame in, new window frames in, planning for the new exterior window completed and preparation for the strengthening of the floor joists also undertaken.  Good work, Barry!

Veteran of the project already, young Joe, was back today taking centre stage, continuing with more electrical first fix.  Planning of the down lighters was also taken care of, all courtesy of Joe.

Robert, Commander in Chief, was on site, off site, wandering around site, on the mobile, on the tools, consulting with us too.  Plaster materials were delivered on site today.  The walls and ceiling will receive the plastering treatment during the next few days.

We were in the unfortunate position of receiving one customer today wanting to view the showroom… aaarrrggghh!  To re-iterate, and these images will confirm, the showroom is a building site and as much as we would love to see you and show off our incredible flooring knowledge we just can't do that right now.  Really sorry folks but bear with us; it'll be worth the wait!

Showroom re-opening on schedule for 1st week in September